Concrete Calculator
Calculators · Added
Two questions, one form. The volume of a pour is pure geometry and comes out the same everywhere. What it takes to fill that volume depends on how you are buying it — cubic yards from a truck, bags from a builders merchant, or cement, sand and stone mixed on site to a nominal ratio. All three are shown, with the method behind each stated rather than assumed.
How to use the concrete calculator
- 1Choose metres and millimetres or feet and inches. Thicknesses are asked for in the smaller unit, which is how they are usually specified.
- 2Pick what you are pouring — slab, footing, wall, round column or square column — and enter its dimensions.
- 3Set how many identical elements there are, so twelve post holes are one calculation rather than twelve.
- 4Add a waste allowance. Ten per cent covers spillage and an over-dug or uneven base.
- 5Choose a nominal mix grade and a bag size to see both the site-mix quantities and the pre-mixed bag count.
Examples
A garage slab
- Input
- 6 m × 3 m × 150 mm thick
- Result
- 2.70 m³ — 2.97 m³ with 10% waste, about 3.9 cubic yards
Past roughly one cubic metre, ready-mix delivered by truck is normally cheaper and far less work than bags.
Post holes for a fence
- Input
- 12 round holes, 300 mm across, 600 mm deep
- Result
- 0.51 m³ — about 33 bags of 80 lb
The diameter is asked for, not the radius. Holes are also rarely as neat as the number, which is what the waste allowance is for.
The same slab mixed on site at M20
- Input
- 2.97 m³ at 1 : 1.5 : 3
- Result
- About 24 bags of cement, 1.04 m³ sand, 2.09 m³ aggregate
The wet volume is multiplied by 1.54 to get the dry volume before it is split, which is where most hand calculations go wrong.
About the concrete calculator
Ordering, and why you should order slightly over
Concrete is unforgiving about arriving short. A pour that runs out halfway leaves a cold joint — a plane where fresh concrete meets partly set concrete and never fully bonds — and that joint is a permanent weakness in exactly the place you did not plan one. Running slightly over costs the price of a small amount of waste. Running short costs the integrity of the element.
That is what the waste allowance here is for, and ten per cent is a reasonable default rather than a law. A slab on a well-prepared, level and compacted sub-base with proper edge shuttering might genuinely use five. A footing in a hand-dug trench through soft ground can swallow twenty, because the trench is wider than it was drawn everywhere the sides crumbled. Look at the base before choosing the number.
Ready-mix is ordered in cubic metres or cubic yards and usually sold in increments, so the figure you calculate becomes the next increment up. Below about a cubic metre, bags generally win on both price and practicality; above it, mixing that much by hand is a long day and the consistency between batches becomes its own problem.
What the grades mean
The M numbers are characteristic compressive strengths in megapascals at 28 days — M20 means 20 MPa. The ratios beside them are the nominal volumetric proportions traditionally used to hit approximately that strength: one part cement, some parts sand, some parts coarse aggregate. The relationship between the ratio and the strength is empirical and it holds only when the materials, the water and the compaction are all reasonable.
Choosing higher than you need is not free. Richer mixes cost more, generate more heat as they cure and shrink more, which means more cracking in a large slab rather than less. The grade should follow the job: mass fill and blinding at the weak end, paths and light floors in the middle, structural elements only to whatever the design specifies.
Curing matters at least as much as the mix, and no calculator can help with it. Concrete gains its strength through a chemical reaction with water, not by drying out, so keeping it damp for the first week — covered, sprayed, or under plastic — is what turns the mix you calculated into the strength it was meant to reach. A perfectly proportioned slab left to bake in the sun on its first day will underperform a rougher one that was kept wet.
Frequently asked questions
Why is the dry volume larger than the concrete it makes?
How many bags of cement is a cubic metre?
Why is water not in the list of quantities?
Should I trust a nominal mix for something structural?
Related tools
Square Footage Calculator
Calculators
Work out floor or plot area from measurements, add a waste allowance and cost the material.
Volume Converter
Converters
Convert litres, millilitres, cubic metres, gallons, pints and cups.
Density Converter
Converters
Convert kg/m³, g/cm³, lb/ft³, lb/gal and other density units.